US military, federal contractors struggle to navigate barriers in unfamiliar environments in the Pacific

Updated: Aug 5


Military officials and federal contractors discussed the challenges facing the construction sector at the 2026 SAME Guam Post Industry Forum held at Dusit Thani Resort from July 29 to 30. Photo by Mar-Vic Cagurangan
Military officials and federal contractors discussed the challenges facing the construction sector at the 2026 SAME Guam Post Industry Forum held at Dusit Thani Resort from July 29 to 30. Photo by Mar-Vic Cagurangan

  By Mar-Vic Cagurangan

 

Federal contractors hustle to fill orders, source materials and recruit workers, with project completion deadlines to beat. A surge in the Department of War’s spending authority entails more contract awards for critical infrastructure projects in the Indo-Pacific region.


The $1.3 trillion National Defense Authorization Act for fiscal 2027 authorizes approximately $2.5 billion for Guam, the Northern Mariana Islands, Palau and the Federated States of Micronesia, where the department has lined up projects crucial to national defense transformation against the backdrop of evolving geopolitical tensions in the region.

 

“We’re not just executing projects. We're trying to get operational capability at locations, not just here in Guam and the second island chain, but across the entire theater,” said Lt. Col. Robert B. Bouffard, command civil engineer at Headquarters Pacific Air Forces.


Guam gets the lion’s share of the total spending authorization for the region. The NDAA authorizes $1.8 billion for the construction of the missile defense system, which consists of mobile components to be installed in 16 locations across the island. The missile defense project is on top of previously planned projects associated with the U.S.-Japan agreement involving the relocation of Marines from Okinawa to Guam. Several projects have either been completed or are ongoing at Marine Corps Base Camp Blaz.


At the 2026 SAME Guam Post Industry Forum held at Dusit Thani Resort last month, military officials highlighted Guam’s key position as a cornerstone of the Pacific Deterrence Initiative, requiring resilient infrastructure, coordinated planning and industry capacity.




Amid China’s growing threats in the region, the Pentagon is expanding logistics capabilities to the CNMI and the freely associated states, where it seeks to upgrade existing infrastructure and public facilities for joint civilian-military use.


The 2027 spending policy measure authorizes $153 million for various projects in the CNMI, including the reconstruction of Tinian's World War II airfield; $384.5 million for port improvements in Palau; and $169.2 million for airport and harbor rehabilitation in Yap.


“As we look at those locations, we're not building something that we're just going to walk away from in a few years,” Bouffard said, adding that the military aims for long-term use of facilities.


The FY2027 NDAA requires a study on the potential benefits of establishing a strategic partnership to assist the U.S. Pacific Command in identifying dual-use infrastructure projects across the Indo-Pacific.


“We don't have enough military to be able to sustain all those, but we’re making sure that they're operational for years to come,” Bouffard added.


More than their logistical value, these strategic islands form another layer of defense, enabling U.S. forces to sustain the fight in the event of conflicts.


While the rapidly changing regional environment calls for acceleration of defense-capability building, military contractors struggle to pick up speed due to a host of barriers, many of which are inherent to isolated locations.


The lack of manpower in Guam and other Pacific islands has always been a chief snag. “This is an extremely challenging labor market,” said Laurie Scott, 

director of strategic client alignment at ECC.


Exacerbating the labor shortage is the challenge of maintaining a workforce that can keep up with shifting engineering standards that meet the military’s increasingly complex requirements. “The type of infrastructure we're building is way more complicated than what we built decades ago,” Scott said. “We're talking about ICD 705 compliant facilities. We're talking about hangars that are supporting autonomous platforms.” 


The building industry itself needs to keep pace with changing demands, Scott added. “Everybody needs to understand the assignment.”


Location is a major issue as well. Surrounded by water, the region’s isolation and distance from the U.S. mainland pose an organic problem that bumps construction costs and limits the availability of material supplies. These have been an albatross for the industry and are “very difficult” to overcome, said Frank Blaz, chief of staff for 356 Theater Support Group of the U.S. Air Force. 


Tinian airfield
Tinian airfield

“It creates this challenge for what can be placed there within that context,” he said. “It doesn't help within (the Pacific Command) that the way to get from point A to point B is through the ocean and through the air. It's not like the (continental U.S.) problem set or the Europe problem set where you can just get on a roadway and bring your assets to locations.”


Scott endorsed the design-bid-build method, which he said can help mitigate the costs and limitations of material supplies. It's really, really important to understand if there's an opportunity to locally source material,” he said. “And if there is material that has to come from outside of a local source, is there an opportunity to identify a world-established supply chain?"


Blaz said “appreciating the problem set of small island nations” and collaborating with them are integral “toward our success holistically for all the Department of War.”



Another impediment to speed is tied to the nature of working in an unfamiliar territory. Differing rules and various environmental challenges in different jurisdictions often cause projects to hit a snag. The National Environmental Protection Act requires that every project go through a review process. Environmental disturbance, particularly in archeological areas, often creates a sore spot between the military and host communities, if not locking projects in lengthy litigation.


“We're not out here trying to just destroy the environment,” Bouffard said, stressing the need for stakeholders to figure out how to navigate the sticking points. “I think the key is making sure that we all have a common goal and a focus on the mission execution.”


Cultural barriers can also cause uncertainties. “I don't want to necessarily say it's the culture, but it is. We've got a lot of folks on both sides in the federal workspace. There's a lot of unknowns,” Brian Weinstein, senior principal at Staniec, said at the industry forum.


“When people get challenged with timelines… they're going to fall back on what they know how to do. So it's a matter of changing that organizational culture to bring everybody along and say, you know what, we're all in this together.”


ADVERTISEMENT


Blaz acknowledged that disagreements over how to accomplish work can get in the way of a project’s movement. “We have a lot of different partners and they don't do things the way we do,” he said. “It's the culture in the Pacific, right? It's definitely not the same culture that we would have in NorthCom or SouthCom.”


Recognizing and appreciating the difference is key. Adjusting perspectives is the first step to arriving at a solution, Blaz said. “We have to get out of that installation mindset. It's not an installation,” he said. “I think the Joint Region Marianas does an excellent job in being able to navigate within that kind of mindset.”


Attitude adjustment is particularly important when working in a sovereign nation, Blaz said. “Maybe we're dealing with some of their properties. It's theirs. (They’re) our partner, our ally, a close state.”


Weinstein underscored the importance of developing mutual trust. “That trust between contractors and government is part of that culture of change and shift to we're-in-this-together (mindset),” he said. “Maybe we're going to stumble and bumble a little bit initially, but we're all going to figure it out and move along together.”

 


Subscribe to

our digital

monthly issue

Pacific Island Times

Guam-CNMI-Palau-FSM

Location:Tumon Sands Plaza

1082 Pale San Vitores Rd.  Tumon Guam 96913

Mailing address: PO Box 11647

                Tamuning GU 96931

Telephone: (671) 929 - 4210

Email: pacificislandtimes@gmail.com

© 2022 Pacific Island Times

bottom of page