The Guam Power Authority (GPA) continues its restoration and post-typhoon recovery efforts. GPA reports that as of 1 p.m. today:
26.0% of the System Load (Customer Demand) has been restored.
83.3% of GPA’s Substation Energization has been restored.
55.6% of GPA’s feeders/ circuits have been energized/restored.
GPA notes that feeders and circuits may be energized only if GPA’s substation is energized and that system load will increase once feeders and circuits are energized.
Customers can contact GPA’s 24-Hour Trouble Dispatch at 475-1472/3/4 or via direct message on GPA’s Facebook page at www.facebook.com/GuamPowerAuthority.
Road Safety for Traffic Control Point:
The Guam Police Department, and other local Law Enforcement Officers and Soldiers with the Guam National Guard continue to maintain traffic flow within our heavily congested intersections. As a reminder to the community, a vehicle approaching a traffic light at any intersection unmanned without a working light should come to a complete stop.
When approaching a manned intersection, it is advised to proceed with caution and be prepared to stop. With heavy rains and minimal lighting, our officers and guardsmen operate with highlighted vests to assist in increasing their visibility for all motorists. Motorists are asked to adhere to all rules and regulations pertaining to Guam Law Title 16.